On 12 November 2026, the Chancellery of the Prime Minister of Poland (KPRM) dismissed a complaint by the Państwo na Czas initiative alleging inadequate supervision by the Ministry of the Interior and Administration (MSWiA) over the timely processing of foreigners’ residence applications. The outcome is recorded in a copy of the official response published by its recipient. On the same day, the Court of Justice of the European Union delivered judgment C-254/25 concerning the processing deadlines for residence applications for studies.

This article examines the complaint, Article 100d, the ministry’s explanation and the relevant Polish and EU court judgments for applicants awaiting temporary or permanent residence permits in Poland. Sources were checked as of 16 November 2026.

Complaint to the Prime Minister’s Chancellery: timeline and response of 12 November 2026

On 17 October 2026, the Państwo na Czas initiative submitted a complaint to KPRM alleging insufficient supervision by MSWiA over voivodes’ compliance with statutory deadlines for deciding residence permit applications.

KPRM requested an explanation from MSWiA on 23 October 2026. A response dated 12 November 2026 carries reference DWS.WSiW.161.1711.3.2026. According to the copy published by the initiative, KPRM dismissed the complaint, citing staffing, organisational and legislative measures described by the ministry.

KPRM’s response concerns the minister’s exercise of supervisory powers under the administrative complaints procedure. The voivode’s compliance with procedural obligations and the duration of an individual application must be assessed separately against the case file.

On 12 November, the initiative announced a renewed submission referring to the CJEU’s judgment C-254/25 delivered that day. The initiative published the text of its renewed complaint. No confirmation that it had been upheld was available as of 16 November.

MSWiA’s position on residence application processing times

KPRM’s response sets out MSWiA’s position that applications by foreign nationals increased in 2016–2025, putting additional pressure on the foreign nationals departments of voivodeship offices. The extent of the workload varies by region.

MSWiA cited additional staffing and funding, development of the MOS electronic platform, efforts to standardise procedures and planned legislative amendments. Day-to-day case allocation, staffing management and office organisation fall within the relevant voivode’s responsibilities.

The ministry provided its assessment of the supervisory steps taken. The Prime Minister’s Chancellery considered that explanation sufficient to dismiss the complaint concerning the minister’s conduct.

Assessing an individual case requires establishing when the application was filed and completed, when the applicable time limit began, what action the voivode took, whether requests for documents were issued and how long the proceedings have actually lasted. These factors determine the available procedural remedies.

Article 100d: which statutory deadlines are suspended until 4 March 2027

Article 100d of Poland’s Act on Assistance to Citizens of Ukraine remains in force until 4 March 2027. For the specified residence-related proceedings conducted by voivodes, statutory decision-making time limits do not start running, and any time limits already running are suspended. The provision applies according to the category of proceedings, including applications submitted by foreign nationals regardless of their nationality.

Article 100d(1) covers applications for temporary residence permits, permanent residence permits and EU long-term resident permits. It also covers specified proceedings to amend temporary residence and work permits, amend certain highly qualified employment permits, and revoke residence permits.

Article 100d(3)–(4) imposes special restrictions on rules concerning administrative inaction, the duty to notify an applicant of a missed deadline, and certain remedies, including financial sanctions for delayed decisions. These restrictions have been challenged before administrative courts.

Administrative proceedings continue while Article 100d applies. Under paragraph 2, acts performed by the voivode during this period remain legally effective. Authorities can collect evidence, request documents and issue decisions.

The legal dispute concerns the prolonged restriction of the right to have a case heard without undue delay. In certain judgments, administrative courts declined to apply extensions of Article 100d after 30 June 2024 on constitutional grounds. The legislative provision remains in force, and reliance on this reasoning requires assessment of the individual case.

CJEU judgment C-254/25 on residence applications for studies

On 12 November 2026, the CJEU delivered judgment C-254/25, A.A. v Wojewoda Śląski (ECLI:EU:C:2026:979). The case arose from an application for a temporary residence permit for studies. The Court interpreted Directive (EU) 2016/801 and Article 47 of the EU Charter of Fundamental Rights concerning effective judicial protection.

Article 34(1) of Directive 2016/801 requires a decision within 90 days of submission of a complete application. The Court examined whether exceptional circumstances, including established force majeure, can justify suspending that period and what safeguards are required concerning the justification and duration of such measures.

The Court distinguished between different sources of pressure on immigration authorities. A sudden and unforeseeable mass influx may require exceptional temporary measures. A gradual increase in applications over several years calls for corresponding organisational and staffing adjustments.

In the operative part of its judgment, the CJEU held that Article 34(1) and (3) of Directive 2016/801, read with Article 47 of the Charter, precludes national rules that, in the absence of force majeure, postpone or suspend the processing period for applications governed by that Directive while excluding an effective court remedy against administrative inaction or delay.

Scope of C-254/25: the dispute concerns residence rights covered by Directive 2016/801, particularly study-related residence. Employment, business, family-based residence, permanent residence and EU long-term residence require separate examination of the relevant laws and case law. The judgment does not order the blanket issue of permits to pending applicants.

Polish Supreme and regional administrative court rulings on administrative inaction

Supreme Administrative Court (NSA), 19 May 2025, II OSK 2921/24. The NSA held that the exceptional circumstances of 2022 did not justify a further extension of Article 100d restrictions beyond 30 June 2024, and declined to apply that extension in its constitutional assessment. At the same time, the NSA partly set aside the lower court’s judgment and dismissed the complaint alleging inaction for the period at issue, because the suspension effective until 30 June 2024 still had to be taken into account.

NSA, 6 August 2026, II OSK 294/26. In a temporary residence case based on employment, the NSA dismissed the Silesian Voivode’s cassation appeal. The Gliwice regional administrative court judgment finding administrative inaction and ordering the voivode to consider the application therefore stood. The NSA judgment is final and concerns that particular employment-based application.

Regional Administrative Court (WSA) in Wrocław, 29 September 2026, IV SAB/Wr 146/26. The Court found the Lower Silesian Voivode inactive in gross breach of the law, ordered consideration of the application within 60 days of receipt of the final judgment and case file, and awarded PLN 500 to the applicant. The official database marks the judgment as not final.

WSA in Wrocław, 29 September 2026, I SAB/Wr 239/26. In an EU long-term residence case, the court found the voivode inactive and ordered an administrative decision within 30 days of receiving the final judgment and the file. It followed the NSA’s analysis of extensions of Article 100d after 30 June 2024. The judgment is marked not final in the official database.

These judgments demonstrate avenues for judicial protection in specific circumstances. The legal basis of residence, the duration and reasons for the delay, completion of formal requirements and the applicable procedural rules remain decisive.

Draft legislation UD408: the proposed changes

KPRM’s response also mentions draft legislation UD408, including a proposed tacit conclusion of proceedings mechanism for a limited set of procedures. Its effects must be assessed against the final legislative text and the commencement dates of its individual provisions.

The Polish Commissioner for Human Rights (RPO), in comments dated 27 July 2026, stated that cases falling within the proposed mechanism accounted for approximately 1.1–1.2% of all applications in 2023–2025. That represents 11–12 cases per 1,000. The proposal would therefore have a limited effect on overall processing times.

The RPO called for stronger staffing in voivodeship offices, better case management and effective judicial remedies. As of 16 November 2026, UD408 is presented here as draft legislation. Its proposed rules are not an existing general procedure for speeding up all residence cases.

What to do when a residence application is taking too long

Before selecting a remedy, review when and how the application was lodged, whether formal requirements were satisfied, the basis for residence, the correspondence history and the voivode’s actions. In temporary residence matters, Article 112a of the Polish Act on Foreigners sets particular conditions for the start of the decision-making period.

– Request an up-to-date case status. Keep the filing confirmation, case number, summonses and the authority’s replies.

– Check whether requirements concerning supporting documents, personal attendance, fingerprints and additional explanations have been met, where applicable.

– Assess whether a formal reminder (ponaglenie) under Article 37 KPA is appropriate, taking Article 100d and any special rules for the relevant permit into account.

– For prolonged inaction, examine the grounds and procedural requirements for an administrative court complaint (skarga na bezczynność lub przewlekłość) under the Law on Proceedings Before Administrative Courts.

– Use judgments relevant to the legal basis of your application and distinguish C-254/25 on study permits from NSA judgments concerning other residence categories.

Court proceedings examine whether the authority complied with its procedural duties and may, where legal conditions are met, require it to determine an application. The substantive decision to grant a residence permit depends on the applicant meeting the requirements for the relevant residence category.

How SKILLDOCS can assist applicants in prolonged proceedings

SKILLDOCS can review the history of proceedings, actual processing times and procedural deadlines, identify relevant judicial rulings and help prepare submissions to the voivode. Learn more about our service: assistance with delayed temporary and permanent residence applications in Poland.

Check whether my case can be expedited

Official sources

– KPRM: response dated 12 November 2026, DWS.WSiW.161.1711.3.2026 ↗ (document copy published by the addressee).

– Państwo na Czas: complaint history and renewed submission ↗ (initiative’s website).

– Polish Journal of Laws 2026 item 1293: Article 100d ↗ (official legislation).

– CJEU: C-254/25, 12 November 2026, ECLI:EU:C:2026:979 ↗ (EUR-Lex).

– NSA: II OSK 2921/24, 19 May 2025 ↗ (official judgments database).

– NSA: II OSK 294/26, 6 August 2026 ↗ (final judgment on employment-based residence).

– WSA in Wrocław: IV SAB/Wr 146/26, 29 September 2026 ↗ (marked as not final in the database).

– WSA in Wrocław: I SAB/Wr 239/26, 29 September 2026 ↗.

– RPO: observations on UD408, 27 July 2026 ↗.

– KPRM: draft bill UD408 ↗.

Sources and case law checked on 16 November 2026. Legal assessment depends on the facts of the individual proceedings and the legislation in force.

Leave a Reply

Your email address will not be published. Required fields are marked *